Base Stabilization and Recycling

Home | Seal Coat | Armor Coat | Base Stabilization and Recycling
 Slurry Seal | Micro Surfacing | Super Patch | Job Opportunities

The top 6"-10" of the base is pulverized, mixed, compacted and recycled into the road base.  Variables in this process include:
Aggregate gradation and soil composition are variables that affect the base stability.

A thorough mixture in the top 6"-10" must be provided.

Adequate drainage must be available.

Emulsified asphalt increases stability.  The proper percentage of asphalt needed for the proper stability is determined by laboratory or engineering analysis.

A 4%-6% asphalt residual in the base has proven to be very successful for this process.

The final step in stabilization is the use of a single or double Seal Coat/ Armor Coat asphaltic overlay.

 

 

 

 

 

 